This orthomosaic, captured on July 28, 2024, shows the housing estate site accelerating from our June 22 update.
Compared to the second image, key changes include:
- Expanded framing: More extensive structural frames and walls in the central and southern sections, with additional building footprints defined.
- Roofing completion: Several houses now have full roofs installed (visible red/brown tiling), enclosing more structures than before.
- Material accumulation: Increased stacks of roofing materials, timber, and steel, along with more scaffolding and temporary enclosures.
- Site infrastructure: Further development of internal roads, pathways, and drainage channels, with cleared areas expanding outward.
- Equipment activity: Additional machinery, including excavators and loaders, concentrated near the northern and eastern boundaries.