Month 10: Exterior Completion and Site Maturation – March 2025

Posted by:

|

On:

|

This orthomosaic, captured on March 30, 2025, shows the housing estate site solidifying from our February 22 update.

Compared to the sixth image, key changes include:

  • Roof and enclosure finalisation: Virtually all houses now fully roofed and enclosed, with visible windows and doors on most structures.
  • Exterior detailing: Added facades, brickwork, and trim on the majority of buildings, enhancing the residential appearance.
  • Landscaping expansion: More turf, gardens, and tree planting around completed houses, particularly in the central and southern areas.
  • Road and driveway paving: Full surfacing of internal roads and driveways, with curbs and markings added.
  • Clean-up and handover prep: Significant reduction in materials and equipment, with cleared spaces for final inspections.